Arundel Habitat For Humanity |
|||||||||||||||||||||||||
Workdays | |
| February 3rd - Interior walls; windows | |
| February 10th - Decks; porches | |
| February 17th -Siding; subs | |
| February 24th - Siding; subs | |
| March 3rd - Siding; subs | |
| March 10th - Painting | |
| March 17th - Painting | |
| March 24th - Cabinets; Painting | |
| March 31st - Closets; hardware | |
| April 7th - Final punchout | |
| April 14th - Landscaping |